Picture
MOE district supervisor testifies at Armow Wind hearing
Saugeen Times
January 12,2014
Heather Pollard, district supervisor of the Owen Sound office of the Ontario Ministry of the Environment (MOE), gave testimony at the Environmental Review Tribunal Thursday afternoon in Kincardine.

Asha James, counsel for the appellants, Ken and Sharon Kroeplin, asked Pollard if any complaints came from post-turbine residents suffering from health effects at the Enbridge Ontario Wind Farm.

"Yes," said Pollard.

"Do you know the number?" asked James.

"350 complaints," said Pollard.

...asked Pollard if complaints had been received from each project.

...several dozen complaints about the CAW turbine.

MOE has heard 139 complaints about the CAW turbine in Port Elgin (in 12 days!)

Bayshore Broadcasting
December 22, 2013

Port Elgin)-Complaints over a single wind turbine in Port Elgin continue to pile up.

Since December 10th, the Ministry of the Environment has received 139 complaints related to the industrial turbine at the Unifor Family Education Centre, formerly the CAW Centre.

The information was brought forward at this week's Saugeen Shores Committee of the Whole meeting as an update to a meeting held August 26th, when there were a series of deputations made by residents who live near the turbine.



 


Comments


Comments are closed.